News
2021-04-29
At 15:18 on October 15, 2019, Taojia Hydropower Station in Tangyuan County of Jiamushi, which was built by the Third Engineering Co., LTD., Heilongjiang Water Resources and Hydropower Group, ushered in a key node - Unit 1 was put into operation, successfully generated electricity and integrated into the National Grid. During power generation, all data are normal and the unit runs smoothly. This indicates that the construction of the main project of Taojia Hydropower Station has been basically completed and entered the final stage of installation and commissioning.
29
2021-04
2021-04-28
The National Energy Administration issued the Guidance on Energy Work in 2021
In order to thoroughly implement the relevant decisions and deployments of the Party Central Committee and The State Council, do a solid job in 2021 energy work, and continue to promote high-quality energy development, the National Energy Administration has formulated the "Guidance on Energy Work in 2021", which is hereby issued.
28
2021-04
2020-04-22
Taojia Power Station, Tangyuan County, Jiamusi, Heilongjiang Province
Taojia Hydropower Station is a low-head runoff type power station mainly for power generation, with an installed capacity of 20.5MW and an annual power generation of 6359.76×104kWh.
22
2020-04
2017-04-28
Recently, after intense installation and commissioning, the ecological flow online monitoring system of the Sixth, Seventh Dangshang Power Stations and the First and Second Lapai Power Stations built by our company in the Danghe River Basin of Subei Mongolia Autonomous County, Gansu Province, has passed the joint acceptance of relevant government departments and has been put into operation. See one of the images below.
28
2017-04
2017-04-24
Yuanjiashan Hydropower Station is located in the Wushui River Basin, Chengbu County, Shaoyang City, with an installed capacity of 2×630kW and an average annual power generation of 6.5 million kWh. The power station was built to generate electricity on July 1, 1984. Since it was put into operation, it has been in operation for more than 30 years. The mechanical and electrical equipment is old and aging, with a high failure rate, and safety hazards are increasing year by year. It is in urgent need of renovation, which includes high-voltage switchgear, excitation, governor, microcomputer integrated automation system, etc. After the transformation, the power station adopts the mode of "fewer people on duty", realizes "one-click start and stop", improves the comprehensive automation level of equipment, reduces operation and maintenance costs, and increases power generation by 12% annually, with obvious economic and social benefits.
24